Upgrades coming to 15th street

A six-week project to repair deteriorated sanitary lines along 15th Street in New Albany will likely begin in August. The suggested course of action is a three-tiered project withthe initial phase to be all sanitary work funded by the sewer board; phase two focuses on repairing stormwater lines; phase three would address lining stormwater joints that are in danger of failing but have not collapsed yet. The first two phases require work under the railroad tracks that run adjacent to 15th Street, which is why they are both to likely be included in the August construction